The Department for Transport (the Department) and Highways England need to take decisive action before the summer if they are to deliver optimal value from their Road Investment Strategy (the Strategy), the National Audit Office said today. The first Road Investment Strategy, which covers the 5 years between April 2015 and March 2020, is an important step towards better long-term planning of England’s strategic road network. But the speed with which it was put together has created risks to deliverability, affordability and value for money which could be carried forward into future road investment periods.
In 2013 the Government committed £11.4 billion of capital funding to improving motorways and A-roads during road period 1 (2015-20), with £7.7 billion for 112 major enhancement projects and other projects designed to, for example, promote cycling, improve air quality and encourage economic growth. The remainder was allocated to the renewal of the existing network.
The Department planned the Strategy in 17 months, in order to publish it before the May 2015 General Election. As a result of this, the Department selected projects without knowing whether they would be the best value and 54 of the 112 projects are currently scheduled to start in 2019/20, which could cause significant disruption to motorists.
The Department chose to set a capital programme which was forecast to exceed funding by £652 million. This ‘over-programming’ had been standard practice in the Highways Agency, as it was expected that some schemes would be delayed or drop out of the portfolio as it was refined. By August 2016, the amount by which forecast capital costs exceeded available funding had increased to £841 million. This is partly because the original investment plan did not take into account all the capital costs, such as post-project evaluations and IT investment, which will cost an estimated £409 million.
So far Highways England has completed six projects on or ahead of schedule and has started construction on a further 19, with 16 planned to be on or ahead of schedule. Highways England forecasts that these projects will be delivered 5% over budget. Highways England met its efficiency savings target of £33 million for 2015-16, and expects to exceed its target for 2016-17, but it has to achieve 70 per cent of its savings target of £1.2 billion in the final two years of the strategy. Highways England is also facing challenges in recruitment of staff to cope with the increased workload. It plans to procure contracts for 57 projects in 2017, compared to six in 2016, but is 19% below its target headcount for procurement and commercial specialists who are in high demand. Highways England has been filling gaps with consultants and interim staff, who cost on average three times more than permanent employees.
Highways England is now reviewing the portfolio of enhancement projects to improve value for money, and has so far identified 16 projects which present a risk to value for money. Highways England and the Department are exploring a number of ways to manage this risk, including revising project design, cancelling projects or delaying projects to enable further assessment of benefits. Highways England has also developed options to bring forward the start dates of up to 10 projects and to delay up to 19 to reduce the number of projects due to start in 2019-20 to establish a smoother delivery profile and reduce disruption to the road network. While this may mean that some stakeholder expectations are not met, value for money depends on the Department and Highways England proceeding, in this and in future road periods, with a realistic and affordable plan.
The NAO has recommended that the Department and Highways England should agree an updated delivery plan for the remainder of the road period, including a clear statement setting out the impact of this updated plan on any work undertaken in the next road period. The Department should also re-evaluate its approach to oversight of Highways England, as the scale and complexity of Highways England’s investment portfolio increases.
“The Department and Highways England need to agree a more realistic and affordable plan if they are to provide optimal value from the Road Investment Strategy”.Highways England has been working to address the risks to deliverability, affordability and value for money that were present in 2015, but we are now nearly two years into the 5-year road investment period. Decisive action needs to be taken before the updated delivery plan is published in the summer if shortcomings in the current strategy are not to be carried over into future road investment periods.”
Amyas Morse, Head of the National Audit Office
Read the full report
Progress with the Road Investment Strategy
Notes for editors
£841 million (7%) The amount by which forecast costs exceed available capital funding for road period 1, as at September 2016 67 Road enhancement projects (out of 112) scheduled to open for traffic in road period 2 (2020/21 to 2024/25) or later, including 54 due to start construction in the final year of road period 1. 16 Projects that Highways England had identified as at risk or not value for money as at February 2017 £11.4 billion Capital funding initially provided over five years for items such as road enhancement and renewals in the first Road Investment Strategy, subsequently increased to £11.9 billion to support new projects or earlier delivery of existing projects. £1.2 billion Efficiency savings target set for Highways England over the five years of road period 1 (2015/16 to 2019/20) 112 Major road enhancement projects in the first Road Investment Strategy, such as smart motorway upgrades and upgrading single-carriageway A –roads to dual carriageway 6 Major road enhancements which opened for traffic by September 2016 £8.3 billion Effectively committed to road enhancement projects in road period 2 (2020/21 to 2024/25)- Press notices and reports are available from the date of publication on the NAO website. Hard copies can be obtained by using the relevant links on our website.
- The National Audit Office scrutinises public spending for Parliament and is independent of government. The Comptroller and Auditor General (C&AG), Sir Amyas Morse KCB, is an Officer of the House of Commons and leads the NAO, which employs some 785 people. The C&AG certifies the accounts of all government departments and many other public sector bodies. He has statutory authority to examine and report to Parliament on whether departments and the bodies they fund have used their resources efficiently, effectively, and with economy. Our studies evaluate the value for money of public spending, nationally and locally. Our recommendations and reports on good practice help government improve public services, and our work led to audited savings of £1.21 billion in 2015.