Today the National Audit Office (NAO) reports that the Ministry of Defence’s (MoD) poor management of three critical infrastructure projects on its nuclear-regulated sites has contributed to a combined cost increase of £1.35 billion and delays of between 1.7 and 6.3 years. After problems in the early stages of the projects, the MoD has made progress, with some of the construction now complete. However, it still needs to manage the remaining commercial risks and learn the lessons for future projects.
The UK’s continuous-at-sea nuclear deterrent relies on a network of equipment, people and infrastructure, often referred to as the Defence Nuclear Enterprise.1 To maintain this network, the MOD needs to complete three complex construction projects, valued at £2.5 billion together.
The three projects are:
- MENSA: a new nuclear warhead assembly and disassembly facility, valued at £1.8 billion, at the Atomic Weapons Establishment (AWE)-operated site in Burghfield (Reading).
- Core production capability (CPC) facilities: upgraded facilities, costing at least £474 million, at the Rolls Royce-operated site in Raynesway (Derby) to produce the latest nuclear reactor core designs.
- Primary build facility: new facilities at the BAE Systems-operated dockyard in Barrow-in-Furness (Cumbria), costing £240 million to upgrade aging facilities and support improved submarine construction techniques.
Along with the risks inherent in all major infrastructure projects, there are unique challenges with these projects. They include the need to comply with additional nuclear-related regulations, the limited pool of suppliers and the complexity of the designs. Problems in the earlier and riskier stages of these projects have caused delays and cost increases.
Some of the designs may have been more costly than necessary, mainly as a result of construction starting before the requirements or designs were fully developed, and changes to the project management or commercial approach. The way that the MoD set up the contracts also means that it, and not its contractors, must foot the bill for these cost increases as it did not share out the financial risks.
The delays to the projects have broader implications for nuclear work, which the MoD must manage. For example, following delays to MENSA, the MoD and AWE had to continue using existing infrastructure. The MoD expects it will have spent £21 million between 2016-17 and 2019-20 on site upgrades to continue to comply with regulations and be able to use the Burghfield site.
The MoD could have learnt more from the early stages of other nuclear infrastructure projects concluded in the UK and elsewhere. Similar challenges arose for the MoD in the 1980s and 1990s, as well as in American defence projects and UK civil nuclear projects, such as at Sellafield.
All the projects have now progressed and most of the facilities are taking shape. The MENSA facility was completed in October 2019, subject to fit out, and the first of the CPC facilities is expected to be completed in early 2020. Construction of one of the Primary build facility buildings is also largely complete. The MoD has made changes to improve its oversight of infrastructure projects and its relationships with contractors and regulators. Some contracts have also been renegotiated or improved for later phases with the aim of reducing costs going forward.
“While these infrastructure projects are complex, the MoD has encountered similar challenges before in its nuclear work. Although it has recently introduced changes to enhance its oversight of the projects and improve its contracts with suppliers, it should have learnt earlier from past mistakes and the experience of others in the nuclear sector. Instead, the MoD’s failure to mitigate commercial and delivery risks early on has led to project delays and cost increases, as well as impacting its wider work.”
Gareth Davies, head of the NAO
Read the full report
Managing infrastructure projects on nuclear-regulated sites
Notes for editors
- The NAO has previously reported on the Defence Nuclear Enterprise in its 2018 report Defence Nuclear Enterprise: a landscape review
- Press notices and reports are available from the date of publication on the NAO website. Hard copies can be obtained by using the relevant links on our website.
- The National Audit Office (NAO) helps Parliament hold government to account for the way it spends public money. It is independent of government and the civil service. The Comptroller and Auditor General (C&AG), Gareth Davies, is an Officer of the House of Commons and leads the NAO. The C&AG certifies the accounts of all government departments and many other public sector bodies. He has statutory authority to examine and report to Parliament on whether government is delivering value for money on behalf of the public, concluding on whether resources have been used efficiently, effectively and with economy. The NAO identifies ways that government can make better use of public money to improve people's lives. It measures this impact annually. In 2018 the NAO's work led to a positive financial impact through reduced costs, improved service delivery, or other benefits to citizens, of £539 million.