Delivering Carrier Strike
Published on:The Department has made good progress since we last reported on Carrier Strike, however it still has a lot to do to meet its targets at the end of 2020.
The Department has made good progress since we last reported on Carrier Strike, however it still has a lot to do to meet its targets at the end of 2020.
The Department has committed electricity consumers and taxpayers to a high cost and risky deal in a changing energy marketplace. We cannot say the Department has maximised the chances that it will achieve value for money.
It is important that the DWP use the hard lessons it learned from implementing its recent programme of welfare reforms to improve how it manages change and anticipates risk.
HS2 is a large, complex and ambitious programme which is facing cost and time pressures. The unrealistic timetable set for HS2 Ltd by the Department means they are not as ready to deliver as they hoped to be at this point.
The Efficiency and Reform Group (ERG) has achieved significant savings but further work should be done to improve the process of gathering and collating evidence.
An interactive summary of the NAO’s presentations at Civil Service Live events, 2015, on four pervasive issues blocking public service improvement.
The purpose of this note is to update the Committee of Public Accounts on developments since the publication of the National Audit Office report in February, particularly the release of the Authority’s second annual report on 23 May.
June 2014.
Optimism bias in public sector projects is not a new phenomenon. But it is one that persists, frequently undermining projects’ value for money as time and cost are under estimated and benefits over estimated. This report uses our back catalogue to illustrate the consequences of over optimism. In doing so, we have identified some contributory factors – such as project complexity and an organisation’s culture of challenge.
This review of five major rail projects highlights lessons the Department for Transport should apply to current and future rail programmes.
The NAO has today published an update for the Public Accounts Committee, detailing developments in the management of the Sellafield site, the UK’s largest and most hazardous nuclear site, and the extent to which progress has been made in decommissioning and cleaning it up.
Defra, the Rural Payments Agency and Government Digital Service have not worked together effectively to deliver the Common Agricultural Policy Delivery Programme.
The new military flying training is 6 years delayed and there is much to do if the MoD is to get the planned benefits from its contractor.
The DfT and Transport for London have done well to protect taxpayers’ interests in Crossrail but risks remain including delivery of the trains.
The lack of predictability of funding for highways authorities has practical implications for road networks and may lead to increased costs in the long term.
The Home Office spent at least £830 million between 2003 and 2015 on the e-borders programme and its successors, but has failed, so far, to deliver the full vision. We cannot, therefore view e-borders as having delivered value for money.
The strategic case for HS2, in terms of increasing rail capacity and generating regional growth, has still to be demonstrated clearly.
All three projects examined by the NAO have experienced significant delays stemming from a range of problems.
The Thames Tideway Tunnel is a planned project to build a large sewer running under the River Thames. It is the Government’s preferred solution to the problem of spills from London’s sewers into the tidal part of the Thames. In response to correspondence, we explain the roles of the different parties, identify potential risks to value for money and set out what we expect good project management to look like. To avoid influencing the outcome of ongoing competitions for the construction and financing of the project, we do not evaluate the value for money of the project and the issues raised do not imply any audit judgement about its performance.
Thameslink aims to reduce overcrowding and journey times. Initial progress has been good but a 3 year delay in awarding the train contract puts the 2018 programme deadline at risk.
We will examine if the Nuclear Decommissioning Authority and Sellafield are taking a sustainable approach to decommissioning.